ISM. Industrial Steel & Manufacturing
All projects

Case study · South Surrey, BC

Sobey’s needed a supply chain. We gave it a frame.

In late 2018, Beedie engaged ISM to detail, fabricate, and install the structural steel for Sobey’s new distribution centre — a half-million square feet that mainland BC and Vancouver Island groceries now move through.

Client Sobey’s Inc.

GC Beedie

Engaged Late 2018

Role Detail · Fabricate · Erect

2,720 tof structural steel, detailed, fabricated, and installed
523,000 ft²of distribution centre under one roof
40,000+ hrsworked in the shop and the field
30 trussessubstantial vertical trusses — 10 tons each
The job

One team, no handoffs. ISM carried this project through all three of its divisions — the steel was modelled in the drawing office, cut and welded in the Delta shop, and bolted up by ISM’s own field crews. At peak, four field crews with twenty-eight ironworkers were erecting structural and miscellaneous steel on site.

The hard part: thirty substantial vertical trusses, each weighing ten tons, designed, fabricated, and erected as part of the package — with significant extra work installed simultaneously with the base building.

Over forty thousand man-hours went through the shop and field to deliver the building — on a schedule where a grocery distribution hub can’t simply wait.

The facility now forms a critical component of Sobey’s supply chain, built to allow continued growth throughout mainland BC and Vancouver Island.

This project “will form a critical component of Sobey’s supply chain immediately and into the future and the facility will allow for continued growth throughout mainland BC and Vancouver Island.”
As featured on ismbc.ca
Next project

Yours could be
the case study.

604-940-4769
7690 Vantage Way
Delta, BC, Canada V4G 1A7
Redesign concept by Nathan Ziemanski — nathanziemanski.com · Not an official ISM property